|
The decision by
Scottish Office civil servants not to disclose the full estimated
cost of the new Holyrood Parliament building was "unnecessary
and wrong" says a hard-hitting report
published today by the Parliament's powerful Audit Committee.
Deputy convener
Nick Johnston said:
"The fact
that the Auditor General undertook an examination of the Holyrood
Project when the building shall not be completed for well over two
years is a sign of the seriousness of concerns expressed over the
project's stewardship and the amount of public expenditure it will
incur.
"The findings
of today's report draw heavily on our own detailed cross-examination
of Muir Russell and Paul Grice, the two respective Accountable Officers
responsible for monitoring costs during the project's split ownership."
The conclusions
and recommendations from the committee's report are as follows:
Conclusions
-
It was not
helpful that, from the outset of the project, a misunderstanding
in the public mind should have been created (by the Scottish Office)
about the full costs of this project (ie the construction costs
plus dependent costs). It was unnecessary and wrong not to disclose
the estimated full costs once they were available.
-
There should
have been much greater transparency in the cost reporting arrangements
for this project. Reporting systems were unsystematic and did
not adequately reflect the political dimension of this project.
-
Bearing in
mind the exceptional and high profile nature of the project, we
consider that the Accountable Officer at the Scottish Office should
have been given information on cost estimates from the earliest
stages. If that information was not forthcoming, then he - as
the Accountable Officer - could have done more to seek it out.
The evidence led the Committee to believe that Mr Russell was
semi-detached from the process.
-
The risk
assessment policies which were in operation prior to the agreement
of a cost plan were clearly insufficient and at odds with HM Treasury
guidance. It is alarming that such fundamental variances in positions
should exist on this matter.
-
The forecast
construction costs of the Holyrood project increased from £62
million to £108 million after the transfer of client responsibility
from the First Minister to the Scottish Parliamentary Corporate
Body in June 1999. As a result of the quality of the evidence
given, we are not in a position to say conclusively when the underlying
causes of the increased costs projected in the late summer of
1999 first arose. However we are persuaded that the redesign of
the chamber that the SPCB instructed in June 1999 did not alter
the forecast construction costs greatly although it did have a
significant impact on the overall progress of the scheme. To our
knowledge, no other fundamental changes were instructed by the
SPCB in the period from handover to August 1999, when the risk
of greatly increased costs was first identified.
-
We do not
have confidence in the former Accountable Officer's view that
the project, when transferred in June 1999, was clearly sustainable
within the budget set.
-
There should
have been an independent review of the state of the project in
June 1999. This would have provided more positive assurance about
the prospects for completion on time and on budget and would have
usefully highlighted the remaining risks and uncertainties to
be faced.
-
We disagree
with the judgement taken by the Clerk and Chief Executive of the
Scottish Parliament, once he became the Accountable Officer, not
to inform the SPCB of the cost consultants' estimate in August
1999 that construction costs could reach £115 million. The
SPCB was entitled to receive all relevant information and it is
unacceptable that this information was withheld from that body.
-
The Spencely
report appears to have been a turning point for the project and
there are several indicators of improved management now in place.
The Holyrood Progress Group has added an element of independent
scrutiny and political control that was not previously evident.
It is noted that there is now a settled design and cost plan in
place.
-
We still
have concerns about the impact of construction inflation and we
have accepted the offer of the Clerk to the Parliament to report
to us the details of the global figure showing the results of
the major tenders and the extent to which it varies from the target
in the cost plan. The trend will be much clearer following the
release of that information.
Recommendations
-
For future
high profile projects we recommend that accountable officers within
the Scottish Administration and other public bodies consider carefully
their responsibilities to answer to Ministers and to the Parliament
for the exercise of their functions. In the interests of good
stewardship and public accountability they should, for any major
project for which they are accountable, ensure that they are informed
and can consider the consequences of the risk of increased costs
becoming real as well as the likelihood of this occurring. Where
the consequences may be so great as to undermine confidence in
the viability or value for money of the project the accountable
officer should consider informing Ministers, who may then inform
the Parliament.
-
The Scottish
Executive should conduct a review of its policy on fee incentivisation
with a view not only to maximising value for money but also achieving
best value.
-
The Scottish
Executive should act to clarify the application of Treasury guidance
on risk assessment and tackle the problematic yet critical issue
of how risk assessment can be achieved in a robust manner but
in a way which does not encourage cost inflation. As part of this
review, we suggest that Ministers may wish to consider guidelines
under which accountable officers present monitoring reports to
them. We recommend that the Scottish Executive considers the issues
pertaining to public reporting and overall public expenditure
planning. We consider that the type of questions which need to
be addressed include defining the circumstances where risk assessment
figures should - as a matter of course - be reported to the Parliament,
and hence made public.
-
For future
major capital projects we recommend that the Executive, and other
public bodies in Scotland, consider the appointment of independent
scrutineers to reinforce project monitoring at critical stages.
BACKGROUND
NOTES
The committee’s
full
report is available on the Parliament’s website or can be
purchased from outlets of the Stationery Office.
|